The Hornsea Wind Farm Project One (Hornsea Project One) is the first project to be developed in the Hornsea Zone, with a total generation capacity of 1,200MW once complete.

We were contracted by J Murphy & Sons (Principal Contractor) to provided 64 HDD drills at various areas throughout the route. This included 92 separate drills with a bore containing 3 x 225mm and 1 x 90mm PE HV Electric duct, 3 circuits at each location. We encountered every possible obstacle which includes; Canals, Rivers, Roads, Motorways, HP Gas, Railways, HV Cables, Water Mains, Primary Sub Station and Environmental Constraints.

We would like to take this opportunity to thank all of the Eco Drill team, the support functions, J Murphy & Sons and Ørsted (previously known as Dong Energy) for their hard work and assistance.